Meeting Date:
|
6/17/2025 - 7:00 PM
|
Category:
|
Consent Agenda A - Routine Business
|
Type:
|
Action
|
Subject:
|
(Item A-11) Resolution 2025-57 Award of Contract and Authorization to Begin Work for the Lincoln Technical Academy Portable Project No. 6391-6912-620-29 (Mrs. Holbert)
|
:
|
|
Enclosure
|
Reso 2025-57 LTA Award.ADA
|
File Attachment:
|
|
Summary:
|
On March 18, 2025, Resolution 2025-24, the Board of Education of Lodi Unified School District authorized staff to advertise and receive bids for the work required for the Lincoln Technical Academy Portable Project No. 6391-6912-620-29.
On May 21, 2025, three (3) bids were received. The lowest and most responsive bidder was Bobo Construction, Inc. in the amount of $611,110.00, which includes a 10 percent owner-controlled contingency.
Approval of this resolution certifies the Award of Contract to Bobo Construction with the total amount to be budgeted $611,110.00.
|
Funding:
|
This project will be funded with Career & Technical Education (CTE) grant funds.
|
Recommendation:
|
It is recommended the Board of Education adopt Resolution 2025-57.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Desiree Wise - Facilities & Maintenance Supervisor
|
|
Signed By:
|
|
Joe Patty - Director III, Maintenance & Operations
|
|
Signed By:
|
|
Edith Holbert - Executive Director of Operations
|
|
Signed By:
|
|
Neil Young - Superintendent
|
|
|
|
|
|
|
|