Review Agenda Item
Meeting Date: 10/15/2024 - 7:00 PM
Category: Consent Agenda A - Routine Business
Type: Action
Subject: (Item A-10) Phase 2 Flooring Replacement at Multiple School Sites Project 3213-4416-7 Deductive Change Order 1 (Mrs. Holbert)
:
Goal D
Enclosure Exhibit A and Exhibit B Phase 2 Flooring Replacement at Multiple School Sites Project Final Deductive Change Order 1
File Attachment:
EX A_Deductive CO1_Ph2Floors_10.15.24_ADA.pdf
EX B_Deductive CO1_Ph2Floors_10.15.24_ADA.pdf
Summary: A change order is the formal documentation of an authorized change in scope to a construction contract. Approval ratifications is presented for the following project: Phase 2 Flooring Replacement at Multiple School Sites Final Approval #1 ($76,992.60). All of the change order items within these Approvals have been authorized in the field by the District, as necessary modifications to complete the project, or to meet District requirements, and are submitted at this time for ratification by the Board of Education. The “A” Exhibits describe the details of the changes for all of the subject projects, while the “B” Exhibit summarizes cumulative contract changes. Flooring was replaced at McAuliffe, Silva & Podesta Schools with a total of 96 rooms.
Funding: This project was funded by ESSER III Funding.
Recommendation: is recommended that the Board of Education approve ratification of the changes itemized and summarize cumulative contract changes in the Attached Exhibits.
Approvals:
Recommended By:
Signed By:
Joe Patty - Director III, Maintenance & Operations
Signed By:
Edith Holbert - Executive Director of Operations
Signed By:
Neil Young - Superintendent