(Item A-14) Resolution 2024-75 Notice of Completion for the Lodi High Aquatics Project No. 0919-8219-1 (Mrs. Holbert)
|
:
|
|
Enclosure
|
LHS Aquatics Final Change Order Reso 2024-75 Notice of Completion Lodi High Aquatics.ADA
|
File Attachment:
|
|
Summary:
|
On December 14 ,2021 the Board of Education adopted Resolution 2021-66 awarding a contract to Diede Construction, Inc. in the total amount of $14,000,000.00, with an approved contract amendment of $1,400,000.00. There was a deductive Change Order of $146,657.50 and the final contract price is $15,253,342.50. All work associated with this project has now been completed. This action will authorize the acceptance of the contract and filing of the NOC for the Lodi High Aquatics Project.
|
Funding:
|
This project was funded with Measure U funds.
|
Recommendation:
|
It is recommended the Board of Education approve Resolution 2024-75.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Edith Holbert - Executive Director of Operations
|
|
Signed By:
|
|
Neil Young - Superintendent
|
|
|
|
|
|
|
|