Subject: (Item A-7) Approval of Revised Construction Project Final Change Order Facility Improvement - John Muir School and Ellerth Larson Elementary School Change Order Paving Project No. 0918-8218 and 0922-8222 (Mr. Kahn)
:
Enclosure EXHIBIT A - Revised Final Change Order No. 1
File Attachment:
Exhibit A Paving Ph III Muir Larson Final CO.ADA.pdf
Summary: A change order is the formal documentation of an authorized change in scope to a construction contract. Approval ratification is presented for the following project: John Muir and E. Larson Schools Parking Lot Project Final Approval ($76,781.93). All of the change order items within these Approvals have been authorized in the field by the District, as necessary modifications to complete the project, or to meet District requirements, and are submitted at this time for ratification by the Board of Education. The “A” Exhibit describe the details of the changes for all of the subject projects and summarize cumulative contract changes.
Funding: This project was funded by Measure U.
Recommendation: It is recommended that the Board of Education approve ratification of the changes itemized and summarize cumulative contract changes in the attached “A” Exhibit.
Approvals:
Recommended By:
Signed By:
Vickie Brum - Planning Analyst II
Signed By:
Leonard Kahn - Chief Business Officer
Signed By:
Neil Young - Associate Superintendent
Signed By:
Cathy Washer - Superintendent